Ca_Law

statute | California

Civil Code - CIV - CIV § 8412

Summary

A direct contractor may not enforce a lien unless the contractor records a claim of lien after the contractor completes the direct contract, and before the earlier of the following times: (a) Ninety days after completion of the work of improvement. (b) Sixty days after the owner

Text

Retrieval chunks

  • #1 | Civil Code - CIV - CIV § 8412

    A direct contractor may not enforce a lien unless the contractor records a claim of lien after the contractor completes the direct contract, and before the earlier of the following times: (a) Ninety days after completion of the work of improvement. (b) Sixty days after the owner records a notice of completion or …