Ca_Law

statute | California

Civil Code - CIV - CIV § 8802

Summary

(a) This section applies to a contract between a public utility and a direct contractor for all or part of a work of improvement. (b) Unless the direct contractor and a subcontractor otherwise agree in writing, within 21 days after receipt of a progress payment from the public ut

Text

Retrieval chunks

  • #1 | Civil Code - CIV - CIV § 8802

    (a) This section applies to a contract between a public utility and a direct contractor for all or part of a work of improvement. (b) Unless the direct contractor and a subcontractor otherwise agree in writing, within 21 days after receipt of a progress payment from the public utility the direct contractor shall pa…