Civil Code - CIV - CIV § 8812

Summary

(a) If an owner withholds a retention from a direct contractor, the owner shall, within 45 days after completion of the work of improvement, pay the retention to the contractor. (b) If part of a work of improvement ultimately will become the property of a public entity, the owner

Text

Retrieval chunks

  • #1 | Civil Code - CIV - CIV § 8812

    (a) If an owner withholds a retention from a direct contractor, the owner shall, within 45 days after completion of the work of improvement, pay the retention to the contractor. (b) If part of a work of improvement ultimately will become the property of a public entity, the owner may condition payment of a retentio…