Ca_Law

statute | California

Civil Code - CIV - CIV § 8844

Summary

(a) If payment of the amount claimed is not made within 10 days after a stop work notice is given, the direct contractor, the direct contractor’s surety, or an owner may in an expedited proceeding in the superior court in the county in which the private work of improvement is loc

Text

Retrieval chunks

  • #1 | Civil Code - CIV - CIV § 8844

    (a) If payment of the amount claimed is not made within 10 days after a stop work notice is given, the direct contractor, the direct contractor’s surety, or an owner may in an expedited proceeding in the superior court in the county in which the private work of improvement is located, seek a judicial determination of…