Education Code - EDC - EDC § 17250.25

Summary

The procurement process for design-build projects shall progress as follows: (a) (1) The school district shall prepare a set of documents setting forth the scope and estimated price of the project. The documents may include, but are not limited to, the size, type, and desired des

Text

Retrieval chunks

  • #1 | Education Code - EDC - EDC § 17250.25

    The procurement process for design-build projects shall progress as follows: (a) (1) The school district shall prepare a set of documents setting forth the scope and estimated price of the project. The documents may include, but are not limited to, the size, type, and desired design character of the project, perfor…

  • #2

    Evidence that the members of the design-build team have completed, or demonstrated the experience, competency, capability, and capacity to complete, projects of similar size, scope, or complexity, and that the proposed key personnel have sufficient experience and training to competently manage and complete the design …

  • #3

    A design-build entity shall not be prequalified or short-listed unless the entity provides an enforceable commitment to the school district that the entity and its subcontractors at every tier will use a skilled and trained workforce to perform all work on the project or contract that falls within an apprenticeable oc…

  • #4

    Where a best value selection method is used, the school district may reserve the right to request proposal revisions and hold discussions and negotiations with responsive proposers, in which case the school district shall so specify in the request for proposals and shall publish separately or incorporate into the req…