Ca_Law

statute | California

Fish and Game Code - FGC - FGC § 2081.7

Summary

(a) Notwithstanding Sections 3511, 4700, 5050, and 5515, and contingent upon the fulfillment of the conditions listed in subdivisions (b), (c), and (d), the department may authorize, under Chapter 1.5 (commencing with Section 2050) or Chapter 10 (commencing with Section 2800), th

Text

Retrieval chunks

  • #1 | Fish and Game Code - FGC - FGC § 2081.7

    (a) Notwithstanding Sections 3511, 4700, 5050, and 5515, and contingent upon the fulfillment of the conditions listed in subdivisions (b), (c), and (d), the department may authorize, under Chapter 1.5 (commencing with Section 2050) or Chapter 10 (commencing with Section 2800), the take of species resulting from impac…

  • #2

    As a condition to acquisition of the water described in paragraph (1), the Department of Water Resources shall be responsible for any environmental impacts, including Salton Sea salinity, related to use or transfer of that water. As a condition to acquisition of the water described in paragraph (2), the Department of …

  • #3

    The requirements of subdivision (b) and (c) of Section 2081 are satisfied as to the species for which take is authorized. (2) The take authorization provides for the development and implementation, in cooperation with federal and state agencies, of an adaptive management process for monitoring the effectiveness of, …

  • #4

    The Secretary of the Resources Agency, in consultation with the department, the Department of Water Resources, the Salton Sea Authority, appropriate air quality districts, and the Salton Sea Advisory Committee, shall undertake a restoration study to determine a preferred alternative for the restoration of the Salton S…

  • #5

    The selection of a preferred alternative consistent with Section 2931, including a proposed funding plan to implement the preferred alternative. The proposed funding plan shall include a determination of the moneys that are, or may be, available to construct and operate the preferred project, including, but not limite…

  • #6

    The specific goals and objectives of the restoration plan. (ii) The range of alternative restoration actions that must be developed and analyzed. (iii) The no action alternative. (iv) The criteria for determining economic and technical feasibility of the alternatives. (v) The range of options for funding the r…